CHP Plant Capstone C1000 + APROVISCapstone
C1000
CHP Plant Capstone C1000 + APROVIS
Capstone
C1000
Year of construction
2015
Condition
Used
Location
Laško 

Basic data
- Machine type:
- CHP Plant Capstone C1000 + APROVIS
- Manufacturer:
- Capstone
- Model:
- C1000
- Year of construction:
- 2015
- Condition:
- used
- Operating hours:
- 50,000 h
Price & Location
- Location:
- Laško, Slovenia

Call
Technical details
Motor and gearbox
Fuel:
domestic gas H
Power details
Input voltage:
400 V
Input frequency:
50 Hz
Input current:
1,444 A
Type of input current:
three-phase
Documentation and certification
Documentation/manual
Cooling
Type of cooling:
air
Further details
Nominal power (apparent):
999 kVA
Rotational speed (max.):
60,000 rpm
Details about the offer
- Listing ID:
- A22903560
- Reference number:
- SPTE-C1000
- Update:
- 08.10.2026
Description
Used natural gas-fired combined heat and power plant for electricity and industrial steam production.
Dkedpjz I T Ekefx Adhju
Main equipment:
• Capstone C1000: five C200 microturbine modules, each rated at 200 kW; electrical output of the complete package: 999 kWe; 400 V / 50 Hz; grid-parallel operation; common acoustic enclosure and control system.
• APROVIS waste heat steam boiler: rated production of 2,000 kg/h of saturated steam at 6 bar(g); maximum allowable pressure 9 bar(g); equipped with two economizer stages for heat recovery.
• Reinhard Simon CKO501G supplementary duct burner: 500 kW, for additional exhaust gas heating upstream of the boiler.
• BIO-KOMP fuel gas booster compressor: 30 kW, maximum flow 340 Nm³/h, discharge pressure 6 bar(g).
The plant has been regularly maintained under a maintenance contract, with components replaced in accordance with the maintenance schedule. One of the five turbine modules is currently non-operational.
Operating hours: T1: 53,191 h; T2: 50,891 h; T3: 51,628 h; T4: 52,691 h; T5: 49,487 h.
The pressure equipment has an inspection certificate issued by an accredited pressure equipment inspection body. Technical documentation is available. Inspection, price and collection terms are subject to agreement.
The listing was translated automatically. Translation errors are possible.
Dkedpjz I T Ekefx Adhju
Main equipment:
• Capstone C1000: five C200 microturbine modules, each rated at 200 kW; electrical output of the complete package: 999 kWe; 400 V / 50 Hz; grid-parallel operation; common acoustic enclosure and control system.
• APROVIS waste heat steam boiler: rated production of 2,000 kg/h of saturated steam at 6 bar(g); maximum allowable pressure 9 bar(g); equipped with two economizer stages for heat recovery.
• Reinhard Simon CKO501G supplementary duct burner: 500 kW, for additional exhaust gas heating upstream of the boiler.
• BIO-KOMP fuel gas booster compressor: 30 kW, maximum flow 340 Nm³/h, discharge pressure 6 bar(g).
The plant has been regularly maintained under a maintenance contract, with components replaced in accordance with the maintenance schedule. One of the five turbine modules is currently non-operational.
Operating hours: T1: 53,191 h; T2: 50,891 h; T3: 51,628 h; T4: 52,691 h; T5: 49,487 h.
The pressure equipment has an inspection certificate issued by an accredited pressure equipment inspection body. Technical documentation is available. Inspection, price and collection terms are subject to agreement.
The listing was translated automatically. Translation errors are possible.
Seller
Note: Register for free or log in, to access all information.
Last online: A week ago
Registered since: 2025
2 listings online
Send inquiry
Telephone & Fax
+386 51 2... show
Your listing has been deleted successfully
An error has occurred